POST Contracts Policy (ASB-04) requires that the Commission approve any contract or interagency agreement greater than or equal to $175,000. After contracts are approved by the Commission, the Executive Director is authorized to approve amendments as follows:
· An extension of time
· An increase of cost up to $25,000
· Modification of contractual services or solutions to other technical
problems
In May 2021, during a self-initiated internal audit of the contract with Allen Comm, POST staff discovered the following issues related to the amendments:
Amendment #1: received Commission approval to contract up to $598,398.00. Subsequent to Commission approval, additional Learning Portal enhancements were added in the amount of $47,000.00 increasing the contract to $645,398.00. The $47,000.00 was not presented to, nor received Commission approval.
Amendment #2: in the amount of $152,145.00 was not presented to, nor received Commission approval.
Amendment #3: in the amount of $1,624,733.00 was not presented to, nor received Commission approval.
|